Tuesday, September 30, 2008

Work is completed !!! --


A great picture above, an aerial view taken on 9/29/08 -- shows both new estuary areas flooded with incoming tide...
Tidal waters begin to fill the new channel for the first time...
It is hot today, and dust from the moving excavators hovers above... It will settle soon as work is completed...
The left edge at 8.0 tide...

Friday, September 26, 2008

Today, the South site is finished!!!!!!!
With great anticipation and excitement, we watch the first tidal waters creep up over the new new marsh ---!!!

Here we go...!

And the tide is in!! Life is already beginning to make it's home in the new waters, even on the first day ~ Great blue heron, killdeer and other birds and salamander footprints are revealed following the tide going out this first day...

Making themselves at home in their new habitat...

Tuesday, September 16, 2008


Excavation continues on the south site. Areas with higher elevations yet need to be brought to lower elevation in order to avoid pooling. All major tidal channels are completed.
Excavation on the north site is nearly completed. What is left is final grading - all major and minor channels are in...

Final steps once these tasks are done will be to carefully reconnect tidal channels to the bay, and remove the berm...!



Tuesday, September 2, 2008

Excavation of new tidal channels begins -- also, at another point on site, excavation revealed historic tidal channels prior to fill, which were excavated as well... Stakes document elevations and channel depths...
Image shows removal of old mill building sites on August 26th...